In Montana, 10% a year if no rate was agreed; the most you can set depends on the deal. Read from Montana's own statutes, agencies and courts, checked November 6, 2026, with every answer quoted below, and a late fee calculator.
10% a year. 10% a year after the money becomes due, unless an express written contract fixes a different rate. The 10% a year is payable on the money § 31-1-106 lists, such as an account stated.
For a homeowner: Greater of 15% or Fed H.15 bank prime + 6 points (prime dated 3 business days before the agreement). Does not apply to regulated lenders (31-1-111, 31-1-112). Merchant-to-merchant finance operations are exempt (31-1-112(2)).
For a business customer: Greater of 15% or Fed H.15 bank prime + 6 points. Same section 31-1-107 cap. A finance operation financing transactions between merchants (as defined in 30-2-104) is exempt from usury limits.
What the text says: Goods sold at retail on pay-on-bill terms: late payment charge up to 1.5% a month, from 30 days after the obligation is incurred. Does NOT apply to money due for intangible services. 31-1-501: retail sales of goods billed for payment on presentation of the bill (not intangible services, PSC-regulated services, real property, health care, or retail installment contracts). 31-1-235: retail installment contracts and retail charge account agreements. It expressly excludes intangible services. It depends: see Mont. Code Ann. § 31-1-501.
Agreed in advance: yes, in the cases below. Any rate other than the 10% legal rate needs an express contract in writing (31-1-106, 31-1-107). The 10% legal rate itself runs without agreement on a writing or an account stated once the money is due.
The construction prompt-payment interest does not reach residential projects under $400,000.
What the text says: 1.5% a month on a payment delayed more than 30 days past the contract due date (owner to contractor, contractor to subcontractor). Written construction contracts between an owner (governmental or private) and a contractor, and subcontracts. Does not apply to residential projects or residential improvements with a total cost under $400,000.
Starts at Montana's 10%, the rate when none was agreed, not a maximum.
Before you charge: read Mont. Code Ann. § 31-1-106 (Legal interest) and the other Montana texts quoted on this page, or ask a lawyer. As of November 6, 2026.
This is a plain-words summary of each state's own laws as of November 6, 2026, not legal advice. Rules have exceptions. Check the state's own text, linked on every state's page, or a lawyer before you charge a late fee or interest.
Compare Montana with every state's answer, or with its neighbours just below.
Every state in one file: Excel and CSV downloads